MINING OPERATIONS
Costa Fuego combines open pit mining methods at Produtora, Alice, Cortadera, and San Antonio, with additional underground block cave methods at Cortadera.

Mining at Productora is completed across 5 phases, with initial phases targetting high-grade, near-surface material in Stage 1 and Stage 2 starter pits.

Mining at Cortadera follows each open pit in turn begining with Cuerpo 1 as Stage 1, Cuerpo 2 as Stage 2, and Cuerpo 3 as Stage 3. Mining at Cuerpo 3 open pit is complete before interaction with the block cave. Cuerpo 1 and 2 pits are used for waste backfill once complete.
PRODUCTION FEED BY MINING LOCATION
The project produces a combination of sulphide concentrator, oxide heap leaching, and low-grade sulphide dump leaching processing feed. Concentrator feed is produced at each mining location, with additional leach circuit feed within the open pits.



PRIMARY PRODUCTION
A 14 year primary production mine life, within a broader 20 year project life span, gives optionality for growth across the project

COMMON QUESTIONS
-
What is the Costa Fuego project?
Read more about Costa Fuego on our project page or in the PFS Infosheet below
READ THE INFOSHEET -
What minerals are at Costa Fuego?
The main economic mineral is chalcopyrite, a sulphide containing copper.
The deposit contains other economic elements such as gold, silver and molybdenum which are included within the "copper equivalent" calculation used to describe the value of the deposit.
ASK A QUESTION
If you would like to ask a question about this page, please contact us using the form below
Subscribe
Stay updated with news & events by joining our mailing list today.
- Terms & Conditions
- Privacy Policy
- © Hot Chili Limited